5-50tph Gold Mining Equipment Manufacturer

Usage: Gold Ore Cyanide Leaching Process
Installation: Engineer Guide
Drawing: Supply
Motor Voltage: 380V
Transport Package: Standard Container, Small Parts by Wooden Box
Specification: 50-500t/h
Customization:
Diamond Member Since 2010

Suppliers with verified business licenses

Manufacturer/Factory & Trading Company

Basic Info.

Model NO.
5-50tph
Trademark
HengXing
Origin
China
Production Capacity
5-500t/H

Product Description

5-50tph Gold Mining Equipment Manufacturer 

gold mining equipment  introduction:

gold mining CIL process is widely used in the newly built leaching plants recent years, and a lot of plants are changing into CIL as well.CIL process is suitable for the treatment of oxidized gold ore with low sulfur content and mud content. It is unsuitable for the gold ore with high grade silver. Generally, the proportion of gold and silver should not exceed 1:5. The best conditions for CIL process in China: PH=10-12, sodium cyanide concentration is not less than 0.015%, the particle size of activated carbon is 1.0-3.35mm, the type of carbon is coconut shell activated carbon, and the slurry concentration is 40-45%.


Gold mining equipment  process: 

Generally speaking the cyanide process can be divided three process crushing grinding and cyaniding. 

First, crushing: to crush the gold ore into your required size, so that in the next step, it can be fed into the ball mill.

 Secondly, use the ball mill to grinding the gold mine into the small sand. so that it can be used into the leaching tank for the cyaniding process.

  

 Thirdly, using the leaching tank and add the carbon in it. After the smelting of the carbon. we can finally get the gold we want. Our tank can be used in both leaching and absorption.

1. Crushing and Screening

After the crushing and screening by the crusher and vibrating screen, the bulk ore (up to 650 mm) can be broken to small size (about 10 mm or even smaller).

Usually, small or medium scale mineral processing plants can meet the requirements after two stages of crushing and one stage of screening. However, large scale mineral processing plants need three or even four stages of crushing to get qualified products.
5-50tph Gold Mining Equipment Manufacturer

 

2. Grinding and Classification

After grinding and classification, the ore material can meet the requirements of leaching (85~95% through 200 mesh).

In the classical process, the grate ball mill and the spiral classifier constitute the first stage grinding and classification unit, and the overflow ball mill and the hydro-cyclone constitute the second stage grinding and grading unit.

If the ore contains some particle gold, the gravity separation process should also be set in the first stage of grinding and grading unit.

5-50tph Gold Mining Equipment Manufacturer

 

3. Thickening

The overflow slurry of classification is only 18-25%, if directly leaching will result in excessive energy cost and reagent consumption. Therefore, thickening is a necessary step. In order to accelerate the settlement, a certain amount of flocculants will be added to enhance the thickening effect.

The overflow will flow to recycle water system, and the underflow will be pumped to the leaching tank.
5-50tph Gold Mining Equipment Manufacturer
 

4. Leaching and Adsorption

Leaching and absorption are simultaneous is the most outstanding feature of CIL process. Generally CIL has 6-10 stages of tanks. The sodium cyanide(or some other leaching reagent) solution is added into the first tank, and gold starts to be leached, most CIL plant will add the activated carbon from the second tank to the last one. Carbon segregation screen is set in every absorption tank's outlet to separate the carbon and slurry. Slurry flow automatically from the first tank to the last one based on the height difference of each stage of tank, while the activated carbon flow reversely through the air lifter. It means that the activated carbon is put into the slurry at the last absorption tank and gold-loaded activated carbon is taken out at the first absorption tank. After screening and washing, the gold-loaded activated carbon will be sent to the desorption operation. After absorption, the gold grade in the tailing solution will reduce to 0.01-0.03g/m³.

5-50tph Gold Mining Equipment Manufacturer

 5. Desorption of Gold-loaded Carbon and Electro-deposition

Gold-loaded carbon and slurry are lifted by carbon pump or air-lifter to separation sieve (the most popular sieve is liner vibrating sieve). Gold-loaded carbon and slurry are separated by water on the sieve surface, and then gold-loaded carbon is sent to carbon storage tank and the slurry and water flow into the first absorption tank.

There are several desorption methods. In China, the general application methods are Zadra desorption method, high temperature and high pressure desorption method (hereinafter referred to as HTHP method) and integral pressure desorption method (hereinafter referred to as IP method).

5-50tph Gold Mining Equipment Manufacturer

Our service :

Hengxing equipment  can provide turkey service for customers, such as engineering consultation, engineering design, equipment manufacturing, packing & transportation, installation & commissioning personnel training etc.

 

About Spare Parts

Hengxing equipment will be dedicated to provide our customers with genuine spare parts with high quality. With our technological advice, the life cycle of your machine can be prolonged and sustained significantly with high effectiveness.

 

About Training

Hengxing equipemnt could offer excellent facilities and comfortable environment and training services to different customers. The training should include product training, safety training, operation training, maintenance know-how, technical know-how training, and regulations training, etc. All of the training is customized to fulfill every customer's expectations. Training programs can be conducted in our workshop, or at customer's site.

 

About Installation and Commissioning

Hengxing equipment  are able to guide the overall installation of whole set production line, including crushing production line and cement equipment production line, etc., which will allow you to start the normal operation of equipment immediately. After installation,we will make inspection of the whole machine commissioning and operation condition and provide you testing data report of installation.


Contact:
Sara Pang
Mobile phone: 0086137 8347 1727
 
 

Send your message to this supplier

*From:
*To:
*Message:

Enter between 20 to 4,000 characters.

This is not what you are looking for? Post a Sourcing Request Now